Wednesday, 5 August 2015

om0017 smu mba summer 2015 IVth sem assignment

Get fully solved assignment. Buy online from website
online store
or
plz drop a mail with your sub code
we will revert you within 2-3 hour or immediate
Charges rs 125/subject and rs 700/semester only.
if urgent then call us on 08791490301, 08273413412


DRIVE: SUMMER 2015
PROGRAM: MBADS (SEM 4/SEM 6) MBAFLEX/ MBA (SEM 4) PGDOMN (SEM 2)
SUBJECT CODE & NAME: OM 0017 – ADVANCED PRODUCTION AND PLANNING CONTROL (4 CREDITS)
BK ID: B2010
MARKS: 60

Qus:1 Explain the flow of information in a production process.
·         Describe why information flow is critical in production planning with a help of an example
·         Describe the flow of information in a production process
·         List the factors that need to considered in a flow of information in a production process
Answer:
Describe why information flow is critical in production planning with a help of an example:

The organisational goals, strategies, and plans need to be communicated well within the organisation, so that the right procedure can be followed to produce the right product at the right time in the right quantity. Thus, in production planning,


Q.2: What are the various techniques of costing?
·         List the various techniques of costing
·         Explain the 6 techniques of costing

Answer:
List the various techniques of costing:

The term “cost” does not stand alone and is always associated with one and the other description such as actual cost, direct cost, explicit


Qus:3 Explain any TEN features of the Advanced Planning and Scheduling (APS) system.
·         List and describe any TEN features of the Advanced Planning and Scheduling (APS) system
Answer:
List and describe any TEN features of the Advanced Planning and Scheduling (APS) system:


Q.4: What are the rules for scheduling Kanban production?
·         List rules for scheduling Kanban production
·         Explain the 6 rules for scheduling Kanban production

Answer:
List rules for scheduling Kanban production:
Scheduling in lean production is done by using kanban cards. Kanban cards are forwarded to the scheduled board, where they are converted into the production job with a sequence of production. Certain rules are followed while scheduling


Q.5: What are factors must be considered while implementing a production planning and control system?
·         Explain the 4 factors to be considered while implementing a production planning and control system

Answer:
Explain the 4 factors to be considered while implementing a production planning and control system:
Manufacturing organizations generally consider certain factors while implementing the system they select. These factors help in the successful implementation of the process. Though these are not the exhaustive factors, but organizations often consider


Q.6: Mention the reasons why manufacturing organizations choose Excel and Visual Basic prototype as planning and scheduling tools.
·         List the 8 reasons why manufacturing organizations choose Excel and Visual Basic prototype as planning and scheduling tools

Answer:
List the 8 reasons why manufacturing organizations choose Excel and Visual Basic prototype as planning and scheduling tools:

The reasons for choosing Excel and Visual Basic prototype as the planning and scheduling tools by manufacturing organisations:
1.      These tools can be used for gathering data, the inputs and outputs of the system and also for creating mock ups of reports. With the

Get fully solved assignment. Buy online from website
online store
or
plz drop a mail with your sub code
we will revert you within 2-3 hour or immediate
Charges rs 125/subject and rs 700/semester only.
if urgent then call us on 08791490301, 08273413412



No comments:

Post a Comment